| |
| Activity Description |
Completion Status |
| |
| Arlington County WPCP - Phase 1 |
| Priority Items of Work |
| Design Package 1(DP-1) |
| 100% Submittal |
Completed |
| |
| Design Package 2(DP-2) |
| 100% Submittal |
Completed |
| |
| Design Package 1A(CP-1A) |
| Notice to Proceed |
July 2004 |
| Contract Includes: |
|
- Carbon Filter Buliding
- East Digestor Tanks
- Line Reactor Tanks
|
|
| Contract Completed by June 2006 as scheduled. |
| Demolition of: |
- Lime Solids Building
- Lime Thickener Structure
- LRT1 Tank
|
|
| Construction of: |
- Partial Electrical Ductbanks
|
|
| Contract Completion: |
Summer 2007 |
| |
| Construction Package 1 (CP-1) |
| Construction Start: |
October 30, 2006 |
| Contract Includes: |
|
- New Equalization Tanks (2)
- New Denitrification Filters (17)
- New Chlorine Contact Tanks (2)
- Electrical Upgrades
- Odor Control Improvements
|
|
| Contract Completion: |
Winter 2009 |
| |
| Construction Package 2 (CP-2) |
| Construction Start: |
September 26, 2006 |
| Contract Includes: |
|
- Secondary Clarifiers 7, 8 & 9 )
- Aeration Tanks 5 & 6
- Ferric Chloride Addition
- Methanol Addition
- Security Fencing
- Wet Weather Facilities
- Emergency Generators (2)
|
|
| Contract Completion: |
Winter 2010 |
| |
| |
| Construction Package 3 (CP-3) |
| Construction Start: |
July 2010 |
| Contract Includes: |
Approximate best estimated dates |
- Upgrading 11 offsite pump stations plus 2 metering stations
|
|
Start |
Scheduled Completion |
| 1. Donaldson Run Pump Station |
In progress |
June 2011 |
| 2. Gulf Run Pump Station |
In progress |
July 2011 |
| 3. Kirkwood Run Pump Station |
In progress |
July 2011 |
| 4. Windy Run Pump Station |
In progress |
July 2011 |
| 5. Roaches Run Pump Station |
In progress |
July 2011 |
| 6. Dover Run Pump Station |
In progress |
July 2011 |
| 7. Riverwood Ejector Station |
April |
July 2011 |
| 8. River Estates Ejector Station |
In progress |
June 2011 |
| 9. Marcey Creek Run Pump Station |
In progress |
June 2011 |
| 10. Rivercrest Run Pump Station |
In progress |
May 2011 |
| 11. Palisades Run Pump Station |
In progress |
April 2011 |
| 12. Lucky Run Meter Station |
Completed |
April 2011 |
| 13. Upper Pimmit Meter Station |
Completed |
April 2011 |
| |
| Contract Completion: |
Summer 2011 |
| |