Proposed Project Schedule/Chronology

 
Activity Description Completion Status
 
Arlington County WPCP - Phase 1
Priority Items of Work
Design Package 1(DP-1)
100% Submittal Completed
 
Design Package 2(DP-2)
100% Submittal Completed
 
Design Package 1A(CP-1A)
Notice to Proceed July 2004
Contract Includes:  
  • Carbon Filter Buliding
  • East Digestor Tanks
  • Line Reactor Tanks
 
Contract Completed by June 2006 as scheduled.
Demolition of:
  • Lime Solids Building
  • Lime Thickener Structure
  • LRT1 Tank
 
Construction of:
  • Partial Electrical Ductbanks
 
Contract Completion: Summer 2007
 
Construction Package 1 (CP-1)
Construction Start: October 30, 2006
Contract Includes:  
  • New Equalization Tanks (2)
  • New Denitrification Filters (17)
  • New Chlorine Contact Tanks (2)
  • Electrical Upgrades
  • Odor Control Improvements
 
Contract Completion: Winter 2009
 
Construction Package 2 (CP-2)
Construction Start: September 26, 2006
Contract Includes:  
  • Secondary Clarifiers 7, 8 & 9 )
  • Aeration Tanks 5 & 6
  • Ferric Chloride Addition
  • Methanol Addition
  • Security Fencing
  • Wet Weather Facilities
  • Emergency Generators (2)
 
Contract Completion: Winter 2010
 
 
Construction Package 3 (CP-3)
Construction Start: July 2010
Contract Includes: Approximate best
estimated dates
  • Upgrading 11 offsite pump stations plus 2 metering stations
Start Scheduled Completion
1. Donaldson Run Pump Station In progress June 2011
2. Gulf Run Pump Station In progress July 2011
3. Kirkwood Run Pump Station In progress July 2011
4. Windy Run Pump Station In progress July 2011
5. Roaches Run Pump Station In progress July 2011
6. Dover Run Pump Station In progress July 2011
7. Riverwood Ejector Station April July 2011
8. River Estates Ejector Station In progress June 2011
9. Marcey Creek Run Pump Station In progress June 2011
10. Rivercrest Run Pump Station In progress May 2011
11. Palisades Run Pump Station In progress April 2011
12. Lucky Run Meter Station Completed April 2011
13. Upper Pimmit Meter Station Completed April 2011
 
Contract Completion: Summer 2011